OAKWOOD PROJECT
NIAGARA REGION
17.11.2025
In our last update for the Oakwood project, we shared that the final Permit and Tender drawing set had been received and reviewed, the required R-Plan for road widening had been deposited with the Land Registry Office, and the Site Plan Agreement had been received and was ready for execution. We also noted that the project was positioned to advance into the permitting and tendering phases.
Since then, additional requirements related to the Site Plan Agreement are being finalized. Specifically, the road widening transfer and parkland dedication appraisal are currently in progress, forming part of the remaining SPA obligations. These steps are procedural in nature and are being managed in parallel to maintain momentum toward permitting.
Overall, the project remains well positioned to proceed into the building permit phase once these final SPA items are completed. With respect to sales, the sales package has been finalized and all marketing materials are fully prepared, positioning the project to launch efficiently in the new year.
Upcoming Milestones:
Building Permit Application: Q1 2026
Timelines:
Official Plan Amendment: N/A
Zoning By-law Amendment: N/A
Draft Plan of Subdivision Conditional Approval: N/A
Draft Plan of Subdivision Approval: N/A
Site Plan Conditional Approval: June 26, 2024
Site Plan Complete Approval: June 13, 2025
Building Permit Issued: Q2 2026
For more information please see the attached and below:
https://fallsgate.ca/
All projected timelines are indicative and reflect current market conditions and planning assumptions. As with any development project, these estimates remain subject to change due to evolving regulatory, market, and construction environments. Accordingly, dates should be considered as targets rather than definitive deadlines.