In our last update for Scenic Heights, we shared that the project was progressing through a redesign aimed at improving efficiency and overall competitiveness in the market.

Since then, the project has advanced significantly. The design has been refined to include a more efficient layout for the residential and retirement buildings (Buildings B and C). The revised concept has been approved in principle by City staff, marking a key milestone in the project’s development.

An additional Consent Application for an easement is underway as part of the remaining requirements.

Upcoming Milestones:

Consent Application (Easement): Q1 2026

Timelines:

Official Plan Amendment: N/A
Zoning By-law Amendment: N/A
Draft Plan of Subdivision Conditional Approval: N/A
Draft Plan of Subdivision Approval: N/A
Site Plan Conditional Approval: May 17, 2023
Site Plan Complete Approval: Q3 2026
Building Permit Issued: Q1 2027

All projected timelines are indicative and reflect current market conditions and planning assumptions. As with any development project, these estimates remain subject to change due to evolving regulatory, market, and construction environments. Accordingly, dates should be considered as targets rather than definitive deadlines.