Projects Update

Q2 2025

back to all projects

Arrowdale (282 Stanley) – Brantford Project
BRANTFORD

25.08.2025

In our last update for Stanley, we highlighted the completion of the Draft Plan of Subdivision (DPS) and efforts towards clearing conditions for the next submission of materials in the condition clearing process.

Since then, our team submitted the First Detailed Engineering on May 9, 2025, and received comments back on July 16, 2025. Through this submission, 50 conditions were addressed and considered complete.

Looking ahead, once City comments on the initial detailed engineering submission have been addressed, we plan to submit the Second Detailed Engineering package by end of August 2025.

Upcoming Milestones:

Condition Clearing: Ongoing
Condition Clearing Submission: Q3 2025

Timelines:

Zoning: Complete
SPA: Q4 2025
Building Permit: Q2 2026

All projected timelines are indicative and reflect current market conditions and planning assumptions. As with any development project, these estimates remain subject to change due to evolving regulatory, market, and construction environments. Accordingly, dates should be considered as targets rather than definitive deadlines.