Projects Update

Q1 2025

back to all projects

88 JAMES CONDOS
ST. CATHARINES

05.05.2025

In our last update for 88 James, we noted that approximately 60% of the units had been sold. Currently, and due to ongoing shifts in the real estate market over the past year, sales activity has remained largely static. We are now preparing for a final launch, with the goal of reaching the 80% sales threshold. This is tentatively planned for post-spring, contingent on market conditions. At this time, there are no further updates to share.

Upcoming Milestones:

Final Launch: Q2 2025

Timelines:

Zoning: Complete
SPA: Complete
Building Permit: Q4 2025

All projected timelines are indicative and reflect current market conditions and planning assumptions. As with any development project, these estimates remain subject to change due to evolving regulatory, market, and construction environments. Accordingly, dates should be considered as targets rather than definitive deadlines.