688 BRANT STREET
BURLINGTON

05.05.2025

In our last project update for 688 Brant, we were progressing through Cycle 2 of the Site Plan Approval (SPA) process, waiting on City comments for our second submission. We also submitted our Minor Variance Application on October 30, 2024, which was officially deemed complete on December 10, 2024 (File Number: A-097-2024).

Since then, Cycle 2 of the Site Plan Approval (SPA) process for 688 Brant has been successfully completed. While the City comments from the second submission were originally expected by November 29th, they were delayed due to additional traffic analysis and third-party audits to assess optimal site access. We received the official comments from the city on January 29th.

In response to the City’s feedback, we’ve proactively collaborated with our adjacent property owner to facilitate shared access through our site. This adjustment has been well-received and highlights a productive partnership with our neighbour.

We are now preparing for the third cycle submission, and our team is currently refining the drawings to address all outstanding comments from Cycle 2. The City remains very supportive of the project and has expressed satisfaction with the progress to date.

Upcoming Milestones:

Site Plan Resubmission (Cycle 3): April 2025
Site Plan Resubmission (Cycle 4): Q3 2025

Timelines:

Zoning: Complete
SPA: Q4 2025
Building Permit: Q1 2026

All projected timelines are indicative and reflect current market conditions and planning assumptions. As with any development project, these estimates remain subject to change due to evolving regulatory, market, and construction environments. Accordingly, dates should be considered as targets rather than definitive deadlines.